Construction Updates,
December 2024

Sunset Gardens
50%

Shore Piling Completed 100%.

Rock Anchoring Completed 100%

Excavation Completed 100%

Raft Foundation Completed 100%

Underground Tanks Completed 100%

Basement Work Completed 100%

Plinth Slab Completed 100%

Ground Slab Work Completed 100%

1st to 3rd Slab Work Completed 100%

4th Slab Work in Progress (20% Completed)

Surrounds Backfilling (90% Completed)

Typical floor mivan setting work in progress