Construction Updates, December 2025

Sunset Gardens
50%

Shore Piling Completed 100%.

Rock Anchoring Completed 100%

Excavation Completed 100%

Raft Foundation Completed 100%

Underground Tanks Completed 100%

Basement Work Completed 100%

Plinth Slab Completed 100%

1st to 15th Slab RCC Completed 100%

16th Slab Completed

Blockwork for 1st floor completed 100%

Blockwork for 2nd floor completed 70%

Blockwork for 3rd to 8th Floor completed 100%

Blockwork for 9th floor work in progress

Concealed Plumbing and Waterproofing 2nd to 7th Floor completed 100%

Concealed Plumbing and Waterproofing 8th Floor work in progress

Infra Work 40% completed