Construction Updates,
February 2025

Sunset Gardens
50%

Shore Piling Completed 100%.

Rock Anchoring Completed 100%

Excavation Completed 100%

Raft Foundation Completed 100%

Underground Tanks Completed 100%

Basement Work Completed 100%

Plinth Slab Completed 100%

Ground Slab Work Completed 100%

1st to 3rd Slab Work Completed 100%

4th Slab Work 70% Completed

Surrounds Backfilling 90% Completed

Typical Floor Mivan Setting Work in Progress