Construction Updates, July 2025

Sunset Gardens
50%

Shore Piling Completed 100%.

Rock Anchoring Completed 100%

Excavation Completed 100%

Raft Foundation Completed 100%

Underground Tanks Completed 100%

Basement Work Completed 100%

Plinth Slab Completed 100%

Ground Slab Work Completed 100%

1st to 8th Slab Completed 100%

9th Slab Work in progress

Blockwork for 1st floor completed 100%

Blockwork for 3rd & 4th Floor completed 100%

Blockwork for 5th floor- work in progress

Infra Work in progress