Construction Updates, August 2024

Sunset Gardens
37%

Shore Piling Completed 100%.

Rock Anchoring Completed 100%

Excavation Completed 100%

Raft Foundation Completed 100%

Underground Tanks Completed 100%

Basement work Completed 100%

Plinth Slab Completed 100%

Ground Floor Work in Progress (20% Completed)