Construction Updates, July 2026.

Sunset Gardens
75%

Excavation Completed 100%

Raft Foundation Completed 100% & Underground Tanks Completed 100%

Basement Work Completed 100%

Plinth Slab Completed 100% ,1st to 22nd Slab RCC Completed 100%, & 23rd Slab RCC work in progress

Blockwork 1st ,3rd to 20th Floor completed 100% & 2nd floor 70% completed. 21st floor work in progress.

Concealed Plumbing and Waterproofing 2nd to 18th Floor completed 100%

Concealed Plumbing and Waterproofing completed till 19th floor & 20th work in progress

Lobby tiling & painting for 3rd floor completed & Internal Painting for 3rd floor completed 100%

Internal electric wiring & plate fixing for 3rd floor completed 

Infra Work 40% completed