Construction Updates, June 2026.

Sunset Gardens
75%

Shore Piling Completed 100%.

Rock Anchoring Completed 100%

Excavation Completed 100%

Raft Foundation Completed 100%

Underground Tanks Completed 100%

Basement Work Completed 100%

Plinth Slab Completed 100%

1st to 22nd Slab RCC Completed 100%

23rd Slab RCC work in progress

Blockwork 1st ,3rd to 20th Floor completed 100% & 2nd floor 70% completed. 21st floor work in progress.

Concealed Plumbing and Waterproofing 2nd to 18th Floor completed 100%

Concealed Plumbing and Waterproofing 19th Floor work in progress

Lobby tiling & painting for 3rd floor completed

Internal Painting for 3rd floor completed 100%

Internal electric wiring & plate fixing for 3rd floor completed 

Infra Work 40% completed