Construction Updates, January 2026.

Sunset Gardens
65%

Shore Piling Completed 100%.

Rock Anchoring Completed 100%

Excavation Completed 100%

Raft Foundation Completed 100%

Underground Tanks Completed 100%

Basement Work Completed 100%

Plinth Slab Completed 100%

1st to 17th Slab RCC Completed 100%

18th Slab RCC work in progress

Blockwork for 1st floor completed 100%

Blockwork for 2nd floor completed 70%

Blockwork for 3rd to 9th Floor completed 100%

Blockwork for 10th floor work in progress

Concealed Plumbing and Waterproofing 2nd to 8th Floor completed 100%

Concealed Plumbing and Waterproofing 9th Floor work in progress

Infra Work 40% completed