Construction Updates, April 2025

Sunset Gardens
50%

Shore Piling Completed 100%.

Rock Anchoring Completed 100%

Excavation Completed 100%

Raft Foundation Completed 100%

Underground Tanks Completed 100%

Basement Work Completed 100%

Plinth Slab Completed 100%

Ground Slab Work Completed 100%

1st to 5th Slab Work Completed 100%

6th Slab Work in progress (30% completed)

Infra Work in progress (20% completed)

Surrounds Backfilling completed 100%