Construction Updates, November 2024

Sunset Gardens
50%

Shore Piling Completed 100%.

Rock Anchoring Completed 100%

Excavation Completed 100%

Raft Foundation Completed 100%

Underground Tanks Completed 100%

Basement Work Completed 100%

Plinth Slab Completed 100%

Ground Slab Work Completed 100%

First Slab Work Completed 100%

2nd Slab Work in Progress (75% completed)

3rd Slab Work in Progress (15% completed)

Surrounds Backfilling (80% completed)