Construction Updates, May 2024

Sunset Gardens
37%

Shore Piling Completed 100%.

Rock Anchoring Completed 100%

Excavation Completed 100%

Raft Foundation Completed 100%

Underground Tanks Completed 100%

Basement work in Progress (65% Completed)